At a paper mill in Maastricht, the network operator could grant the mill a connection for a second electric boiler, provided the mill could turn down its demand when the grid was busy. For an investor, those last words can change the value of the whole proposal. A project is ready for its next decision when the people taking the risk can see what the asset is allowed to do, what it has promised its customer and what happens to the money when the two diverge.

That test works at more than one stage. A developer may have enough evidence to pay for a design study today. A lender considering construction finance needs to know whether the design can fulfil the service agreement throughout the proposed loan. An institution buying an interest in a fund needs to know which of these decisions its manager is allowed to take.

The difference between 24 megawatts and 24 dependable megawatts

In June 2024, Dutch network operator Enexis announced a flexibility agreement with Sappi’s Maastricht paper mill. The mill had 37 MW of contracted capacity. It could make 9 MW of its existing demand flexible because its electric boiler did not need to operate at full power all day. Sappi wanted a further 15 MW for a second boiler. Enexis agreed to allow it on condition that the entire additional 15 MW could also be flexibly controlled. Taken together, the two commitments accounted for the 24 MW in the announcement. Enexis’s account of the Sappi agreement, in Dutch

The second boiler gained a route to more grid capacity. The operator gained the ability to call on flexibility at a congested part of the network. A reader who enters “24 MW available” in a project model loses the condition that made the agreement possible. The announcement gives the terms Enexis disclosed. Detailed dispatch rights, heat delivery, tariffs and the mill’s financial returns would require separate evidence.

The IEA describes non-firm grid access as one response to connection constraints. An offer limiting consumption or generation can work for a plant that can change when it operates. The customer has to accept the interruptions too. IEA’s analysis of grids and flexible connections

Follow one interrupted shift to the invoice

Consider a separate, illustrative heat project. A factory needs 4 MW of useful heat continuously for a three-hour shift. During that shift the network restricts electricity enough to take the project’s boiler offline. The energy that must come from somewhere else is 4 MW × 3 hours = 12 MWh of useful heat.

That calculation settles one question. The equipment also has to deliver heat at the required temperature and rate. A thermal store must have enough usable energy, sufficient discharge power and time to recharge before the next interruption. A backup boiler needs a fuel supply and someone able to operate it. Changing the factory’s schedule might avoid both investments if the production team can move that shift. These options have different costs and different consequences for the customer.

Now follow the invoice. If the project earns money only on heat delivered during those three hours, an interruption can remove revenue from the model. If it promises continuous service, the remedy for a shortfall depends on its contract. If the customer has agreed to scheduled interruptions, the question becomes how much notice the operator must give. A project team can waste months debating the price of electricity before two people notice they have modelled different promises.

The documents that ought to agree

Put these side by side Discrepancy to look for Who can establish the answer?
Grid offer and operating plan The model assumes full power in hours when the network may restrict consumption Network operator and connection lead
Customer specification and design The equipment supplies the annual heat quantity but misses the required shift, temperature or delivery rate Customer’s production team and design engineer
Supply agreement and financing model The forecast counts a payment that the customer need not make during an interruption Contracting parties and project finance team
Financing approval and drawdown conditions A board decision to proceed is being treated as cash available to pay a contractor Project sponsor, lender and advisers

Give each discrepancy to one named owner. Ask them to return with either a corrected assumption or the document that supports the original. An investment paper can then say what the money buys. It might fund an engineering study to test storage and backup against the hours the customer needs. The European Investment Bank’s project cycle separates appraisal, approval, signature and disbursement. In any transaction, the signed documents govern the conditions for payment. EIB project cycle

Where should the developer and the allocator go?

An institutional investor comparing infrastructure managers could use the Infrastructure Investor Global Summit, Berlin, the 22nd to the 25th of February 2027. It has a dedicated limited-partner programme across infrastructure sectors. For an energy-transition strategy, ask a manager whether the fund can pay to investigate a connection constraint, finance a project after that constraint is resolved, or buy the operating asset after construction. The answers describe three different exposures. Berlin investor programme · How investment mandates work

For the developer, customer or utility trying to settle the operating question, The Decision Room’s proposed energy work in Zürich in May 2027 asks which industrial power constraints are worth paying to resolve. A case can begin with one hour when the plant cannot do what the contract promises. Give the team the public or shareable facts and identify the people able to reconcile them. The team can then decide whether to prepare a working session. Edition II programme

We publish this guide and meet independently during Climate Week Zurich in May 2027. A confirmed place includes the Capital Floor. Your offer states any Roundtable or Workshop place. If one session decides whether you travel, name it when you request consideration. Cases and participation