On the 14th of October 2026, the developer GIGA Storage signed an agreement with Amprion to connect its proposed Albatross battery to the German transmission grid at Merzen. Nine days later the project reached financial close. The developer reported a €260 million debt package and said it had also settled the permits, land contracts and supplier contracts it needed. The grid agreement settled the connection at Merzen. Financial close depended on all of those agreements together. Grid connection announcement · Developer’s account of financial close
A factory faces its own connection question. It needs to know whether it can draw enough electricity, at the place and time its production line needs it, on terms the business can afford. A grid connection, a supply contract and a power purchase agreement each settle a different part of the answer. Compare them against the same shifts, commissioning tests and customer delivery dates.
Matching daily totals and a twelve-hour shortfall
A hypothetical plant draws 2 megawatts continuously. In 24 hours it needs 48 megawatt-hours. Suppose its purchasing arrangement covers a generator producing 4 megawatts for twelve hours and nothing for the next twelve. The generation also adds up to 48 megawatt-hours.
| Twelve-hour period | The plant uses | The generator produces | Exposure to settle |
|---|---|---|---|
| Generator on | 24 MWh | 48 MWh | 24 MWh surplus |
| Generator off | 24 MWh | 0 MWh | 24 MWh shortfall |
Now give those hours different prices. Suppose the surplus can be sold for €30 per MWh and replacement electricity costs €90 per MWh in the hours the generator is off. Selling the surplus brings in €720. Replacing the shortfall costs €2,160. The difference is €1,440 for that day before any fees. The daily volumes still matched.
This illustration assumes the plant can buy and sell at those prices, the two parties settle those quantities as described, and there are no losses, storage or changes in production. It measures the cost of the mismatch alone. To obtain a total electricity bill, add the underlying contract settlement and other applicable charges. A financially settled PPA changes who makes payments when the reference price moves. Physical supply at the factory’s own meter is a separate requirement. World Bank overview of physical and financial PPAs
What can happen at the site on the first Monday?
Ask the network operator what capacity the site can draw during commissioning, when the full contracted capacity starts and under what conditions it can be restricted. An application, an offer and a signed connection agreement each support different assumptions. The IEA has documented grid constraints affecting new demand and generation. The answer for a given factory has to come from the people and documents governing that connection. IEA on grid constraints
Next ask the plant manager to describe the first test that requires several systems to run at once. Ask which other load must be switched off to make room for it, and whether the team can stagger the tests and still satisfy the equipment supplier’s handover requirements. If an interruption would spoil a batch or require a long restart, price those consequences alongside the electricity charge. The cost of a contract allowing curtailment depends on whether the company can move a shift or runs a continuous line.
Albatross shows the difference between power and energy. The developer gives the planned battery’s power as 350 MW and its energy capacity as 1,400 MWh. Those figures give a nominal four hours at full power. Whether a factory could use a battery to bridge a constraint depends on the duration of its shortfall, usable capacity, losses and the grid arrangements at its own site. The plant in our example lacks 2 MW for twelve hours, a 24 MWh gap. A remedy has to cover both figures. Albatross project parameters
Compare the offers on the factory’s clock
Give each supplier the same load profile and proposed hours of operation. Ask it to identify how shortfalls are supplied, how surpluses settle, who balances the account and whether the reference price is for the same place and hours as the plant’s bill. Record network charges and any collateral the buyer has to post. Count any cash tied up as security alongside the expected price per unit. European Commission on longer-term electricity contracts
Change one fact at a time. Put energisation back three months and identify the first customer or contractor payment that moves. Change the second shift and recalculate what must be bought outside the contract. Put a higher price against the hours of shortfall. A finance team can then ask procurement which changes the contract can cover and which the business must fund as a risk.
Bring the missing hour to Zürich
A project team can make a power discussion concrete with one sheet. Set out the available grid position, the period of greatest shortfall, the equipment or customer commitment that depends on it, and the last date on which the team can still choose another route. An operator can explain what interruption does to production. A supplier or financier can explain which part of the exposure it could take. That is the sort of case The Decision Room’s proposed Energy & Decarbonisation work can examine in May 2027. Explore Edition II · Describe your contribution
For the wider construction decision, see first-of-a-kind plant finance. To compare where plant teams and potential counterparts can meet, read the European industrial decarbonisation event guide.